Skip to content
Free Shipping on All Orders
Free Shipping on All Orders
Installation Guide · Clear (GLK-C5) & Amber (GLK-A5)

How to Install Gravel-Lok

A single-component, moisture-curing polyurethane binder blended with clean, washed stone to build a permeable, durable bonded-stone surface. Clear and Amber install the same way — this guide covers the recommended mix method, coverage rates, and handling details, step by step.

Method
Mix / Pour
Mix ratio
20–24 oz / bucket
Cure window
50–90°F
Shipping
Free
Overview

Two Formulas, One Process

Gravel-Lok comes in two formulas — Clear and Amber — that install in exactly the same way; the only difference is appearance and recommended use. The steps below apply to both. Choose your formula first, then follow the mix method for a permeable surface suited to paths, patios, tree pits, and drainage edges.

00

Clear or Amber: Which Formula

Both formulas use the identical installation process, coverage rates, and cure requirements. Choose based on the look you want and how the surface will be used.

Gravel-Lok Clear GLK-C5
AppearanceColorless to light yellow. UV-stable — won't discolor stone.
Best onWhite, light, or any color stone where you want the natural tone preserved.
UsePathways, patios, garden paths, french drains, city tree pits, stone scaping.
TrafficSuitable for higher-use pedestrian surfaces.
Gravel-Lok Amber GLK-A5
AppearanceWarm amber tone, matte finish. Not UV-stable — will discolor light / white stone.
Best onDarker or natural stone where a warm, matte look is desired.
UseGarden paths with minimal use, french drains, stone scaping, tree surrounds.
NoteMatte finish becomes fully visible 2–6 months after application.

Deciding between the two? See the Color Comparison (Amber vs. Clear) guide for side-by-side visuals.

01

Before You Start

Choose the stone

Use clean, washed stone so the binder can bond. Both rounded and angular stone work — angular stone interlocks and adds stability over time.

Set the depth

Finished depth should be at least 3× your stone size — ½" stone needs 1.5" minimum. The pour method needs 2.5" minimum.

Watch the temperature

Install only when temperatures hold between 50°F and 90°F for 24 hours after application. Cold or damp air stalls the cure.

Dry everything

Stone must be 100% dry before mixing. Residual moisture makes the resin set too fast — a common cause of premature hardening.

STEPS

Mix Method, Step by Step

The mix method suits most residential paths and patios: blend binder into the stone in a bucket, place it, level it, let it cure, then seal the top with a roll coat.

Rinsing aggregate stone with a hose to wash out dust before drying
Step 01

Wash and fully dry the stone

Rinse aggregate to remove dust and fines, then let it dry completely. Dry stone is non-negotiable — trapped moisture accelerates the reaction and a batch can set before you place it.

Stone: washed, rounded or angular Moisture: 100% dry
Pouring measured Gravel-Lok binder from a jug into a bucket of dry stone
Step 02

Measure the binder into the stone

Work in batches of roughly one 5-gallon bucket of stone (about 50 lbs). Add binder to the stone — never over the limit, or the mix foams and weakens.

Max: 20–24 oz liquid Per: 5-gal bucket (~50 lb)
Mixing stone and binder with a drill paddle until every stone is coated
Step 03

Mix until every stone is coated

Blend thoroughly — a drill paddle or mortar mixer works well — until each stone carries a thin, even film of binder. Consistent coating gives the finished surface its strength.

Look for: uniform sheen Avoid: pooling / foam
Rolling out geotextile separation fabric across the prepared installation area
Step 04

Install geotextile fabric in the installation location

Lay a geotextile separation fabric across the prepared base before placing stone. It separates the aggregate from the subgrade, stabilizes the surface, and helps maintain permeability over time. Overlap seams and extend the fabric to the edges of the installation area.

Function: separation + stabilization Seams: overlap, cover full area
Screeding coated Gravel-Lok stone level with a straight board to set the finished depth
Step 05

Place and level to depth

Spread the coated stone over your prepared base and screed it level. Keep finished depth at least three times the stone diameter so the surface locks together and stays put.

Min depth: 3× stone size Concrete base? wet roll coat first
Applying a light roll coat of binder over the cured Gravel-Lok surface with a roller
Step 06

Cure, Then Apply the Roll Coat

Leave the placed surface undisturbed to moisture-cure for at least 24 hours within the temperature window. Once it has cured, apply a light roll coat of binder across the top to lock the surface and add sheen.

Cure first: 50–90°F, 24 hrs+ Then roll coat: ~90 SF / gal
08

How Much You'll Need

Coverage depends on depth and method. These are the published rates — plan the roll coat separately from the mix or pour.

Mix method — binder coverage by finished thickness
Finished thicknessCoverageNotes
1"37.2 SF / galThinnest usable layer
1.5"24.8 SF / galCommon path depth
2"18.6 SF / galHeavier-use surfaces
Roll coat90 SF / galTop seal, applied separately
Pour method — for larger areas (2.5" minimum)
ApplicationCoverageNotes
1 light pour19 SF / galPoured onto dry stone
2 light pours14 SF / gal combinedRecommended for durability
Roll coat90 SF / galTop seal, applied separately

One 5-gallon container ≈ 640 oz of binder. At the 20–24 oz-per-bucket mix rate that covers a substantial area — run your exact square footage through the Gravel-Lok Coverage Calculator for a precise number.

09

Get These Right

Don't over-add binder. Staying at or below 20–24 oz per 5-gallon bucket of stone prevents foaming. Excess liquid weakens the bond and clouds the finish.

Wet stone sets fast. If a batch starts hardening sooner than expected, the stone likely wasn't fully dry after washing. Dry thoroughly before mixing.

Match the formula to your stone. Clear is UV-stable and won't discolor light or white stone. Amber is not UV-stable and will tint light stone with a warm matte finish that develops over 2–6 months — great on darker stone, but not for keeping whites bright.

Installing over concrete? Add a roll coat to the concrete and, while it's still wet, place the mixed Gravel-Lok stone on top so it bonds to the slab.

Want ADA compliance? Use 1/8" to 1/2" size stones. The bonded surface stays firm, stable, and permeable at that gradation.

10

Installation FAQ

How long before the surface can be walked on?
Keep the surface undisturbed while it moisture-cures within the 50–90°F window. Cure time lengthens in cooler or more humid conditions, so plan the pour when a stable 24-hour window is in the forecast.
Can I use Gravel-Lok for a driveway?
Vehicular applications require additional base support beyond a standard pedestrian install. Review the driveway and vehicular application documentation before proceeding.
What stone size should I choose?
Use clean, washed stone — both rounded and angular work, though angular stone interlocks and adds stability over time. For ADA-compliant firm-and-stable surfaces, use 1/8" to 1/2" gradation. Set finished depth to at least three times the stone diameter.
How do I calculate how much I need?
Use the published coverage rates above as a starting point, then enter your exact square footage and depth in the Gravel-Lok Coverage Calculator for a precise binder quantity.
Reference only. Always follow the printed instructions in the product brochure and on the back of the container, which govern your specific batch. This guide summarizes the published mix method, coverage rates, and handling notes for Gravel-Lok Clear (GLK-C5) and Amber (GLK-A5). For driveways and vehicular use, additional base support is required.